Concrete for a 100 ft curb and gutter

A 100 ft run of curb-and-gutter: a 6 in × 18 in curb with a 12 in × 4 in gutter pan. Both cross-sections are added before multiplying by the run. That is 108.33 cubic feet, or 4.01 cubic yards: 181 bags of 80 lb premix or 241 bags of 60 lb, before any waste.

Concrete needed

4.01cubic yards· 3.068 m³· 108.33 ft³
Bags of premix needed for concrete for a 100 ft curb and gutter, by bag size.
Bag sizeBags needed
40 lb362
60 lb241
80 lb181
25 kg263
30 kg219
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Ready-mix
4.01 yd³ is comfortably past the short-load band and inside a single truck. Ready-mix will almost certainly be cheaper than bags here, and it arrives as one continuous pour instead of however many batches you can mix in a row. The bag count above is for costing the comparison, not for planning the day.

Same job, other sizes

Curb and gutter

Volume for each size. The order columns add 10%, the top of the 5-10% waste allowance, and round bags up.
Sizeft³yd³yd³ to order (+10%)80 lb bags (+10%)60 lb bags (+10%)
20 ft run21.670.80.884053
50 ft run54.172.012.21100133
100 ft run (this page)108.334.014.41199265

Per unit

Each foot of this curb and gutter holds 1.08 ft³, so one cubic yard pours about 24.9 ft of it.

One 80 lb bag fills about 7 in of run.

Change the dimensions in the curb calculator. Why every count rounds up: how many bags of concrete you need.

At this size

What changes on a 100 ft curb and gutter

Mixing or ordering it

181 × 80 lb bags is 4.01 yd³ - about 91 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 181 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A curb is a long prism: its cross-section (width × height) times the run. For curb-and-gutter, the flat gutter pan (width × thickness) is added to the cross-section before multiplying by the length.

That volume - 108.33 ft³ - is divided by 27 to give 4.01 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 181 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

curb Wcurb Hgutter Wcross-section × runCURB & GUTTER