A 100 ft run of plain curb, 6 in wide and 18 in tall. The volume is the curb cross-section times the run.

Concrete needed

2.78cubic yards· 2.124· 75 ft³
Bag sizeBags needed
40 lb250
60 lb167
80 lb125
25 kg182
30 kg152
Planning estimate, with no waste allowance included. Add 5–10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.

How it is worked out

A curb is a long prism: its cross-section (width × height) times the run. For curb-and-gutter, the flat gutter pan (width × thickness) is added to the cross-section before multiplying by the length.

That volume — 75 ft³ — is divided by 27 to give 2.78 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 125 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge — worth a call before you choose between bags and a truck.