Curb

Concrete for a 20 ft curb and gutter

A 20 ft run of curb-and-gutter: a 6 in × 18 in curb with a 12 in × 4 in gutter pan. Both cross-sections are added before multiplying by the run. That is 21.67 cubic feet, or 0.8 cubic yards: 37 bags of 80 lb premix or 49 bags of 60 lb, before any waste.

Concrete needed

0.8cubic yards· 0.614 m³· 21.67 ft³
Bags of premix needed for concrete for a 20 ft curb and gutter, by bag size.
Bag sizeBags needed
40 lb73
60 lb49
80 lb37
25 kg53
30 kg44
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Bags
0.8 yd³ is under a ready-mix supplier's usual one-yard minimum, so bags are the answer whatever the price per yard says. Buy a couple more than the count above and return what you do not open.

Same job, other sizes

Curb and gutter

Volume for each size. The order columns add 10%, the top of the 5-10% waste allowance, and round bags up.
Sizeft³yd³yd³ to order (+10%)80 lb bags (+10%)60 lb bags (+10%)
20 ft run (this page)21.670.80.884053
50 ft run54.172.012.21100133
100 ft run108.334.014.41199265

Per unit

Each foot of this curb and gutter holds 1.08 ft³, so one cubic yard pours about 24.9 ft of it.

One 80 lb bag fills about 7 in of run.

Change the dimensions in the curb calculator. Why every count rounds up: how many bags of concrete you need.

At this size

What changes on a 20 ft curb and gutter

Mixing or ordering it

37 × 80 lb bags is 0.8 yd³, which is about 19 batches in a 6 ft³ site mixer at two bags a batch. That is a comfortable half-day for two people - one mixing, one placing - and at 0.8 yd³ you are under the one-yard minimum most ready-mix suppliers will deliver, so bagging it is the route regardless of price.

How it is worked out

A curb is a long prism: its cross-section (width × height) times the run. For curb-and-gutter, the flat gutter pan (width × thickness) is added to the cross-section before multiplying by the length.

That volume - 21.67 ft³ - is divided by 27 to give 0.8 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 37 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

curb Wcurb Hgutter Wcross-section × runCURB & GUTTER

Nearby

Next sizes up and down