Concrete for a 50 ft footing, 16×8 in

A 50 ft run of 16 in × 8 in strip footing. The volume is the trench cross-section times the run. That is 44.44 cubic feet, or 1.65 cubic yards: 75 bags of 80 lb premix or 99 bags of 60 lb, before any waste.

Concrete needed

1.65cubic yards· 1.259 m³· 44.44 ft³
Bags of premix needed for concrete for a 50 ft footing, 16×8 in, by bag size.
Bag sizeBags needed
40 lb149
60 lb99
80 lb75
25 kg108
30 kg90
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Either - check the short-load fee
1.65 yd³ clears the usual one-yard minimum but sits in the short-load band, where most suppliers add a surcharge for anything under about 3-4 yd³. That fee is what decides it: get it quoted, add it to the yard price, and compare against the bag count above at your own bag price.

Same job, other sizes

16 × 8 in footing

Volume for each size. The order columns add 10%, the top of the 5-10% waste allowance, and round bags up.
Sizeft³yd³yd³ to order (+10%)80 lb bags (+10%)60 lb bags (+10%)
10 ft run8.890.330.361722
15 ft run13.330.490.542533
20 ft run17.780.660.723344
24 ft run21.330.790.874053
30 ft run26.670.991.094966
40 ft run35.561.321.456687
50 ft run (this page)44.441.651.8182109
60 ft run53.331.982.1798131
80 ft run71.112.632.9131174
100 ft run88.893.293.62163218

At this size

What changes on a 50 ft footing, 16×8 in

Mixing or ordering it

75 × 80 lb bags is 1.65 yd³ and roughly 38 mixer batches. This is the crossover point: bagging it is a full day with a mixer and at least two people, and the concrete has to keep arriving faster than the placed edge stiffens. Price 1.65 yd³ of ready-mix, short-load surcharge included, against 75 bags at your own bag price before you commit to a day of mixing.

How it is worked out

A strip footing is a long rectangular prism under a wall; a spread footing is a pad under a column. Either way the volume is length × width × depth. Enter the total run of the footing as the length, and the trench cross-section as width × depth.

That volume - 44.44 ft³ - is divided by 27 to give 1.65 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 75 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

wall aboverun / lengthdepthwidth acrossSTRIP FOOTING