Concrete for a 60 ft footing, 24×12 in

A 60 ft run of 24 in × 12 in strip footing. The volume is simply the trench cross-section times the run; here it is worked out with the bag counts.

Concrete needed

4.44cubic yards· 3.398· 120 ft³
Bag sizeBags needed
40 lb400
60 lb267
80 lb200
25 kg291
30 kg242
Planning estimate, with no waste allowance included. Add 5–10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.

How it is worked out

A strip footing is a long rectangular prism under a wall; a spread footing is a pad under a column. Either way the volume is length × width × depth. Enter the total run of the footing as the length, and the trench cross-section as width × depth.

That volume — 120 ft³ — is divided by 27 to give 4.44 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 200 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge — worth a call before you choose between bags and a truck.

Formwork

What is being measured

wall aboverun / lengthdepthwidth acrossSTRIP FOOTING